AVK Wastewater treatment plant - phyto-purification

Case

New wastewater treatment plant

To support the modernisation and extension of the wastewater network in the district of Saint-André-Treize-Voies (Montréverd), the Terres de Montaigu urban community opted to replace its ageing lagoon-based treatment facility – no longer adequate in terms of capacity – with a more compact and efficient phyto‑purification plant.

In this context, Noria Conception Hydraulique was appointed as works contractor, entrusted with the installation, commissioning and oversight of a complete set of AVK knife gate valves.

A renewal project driven by automation

The aim of the project was to substitute the former station with a more compact solution based on a reed bed filtration process (French constructed wetlands), recognised for its environmental performance. The chosen configuration features two filtration stages, divided into 9 and 6 separate beds. This concentrated layout requires frequent switching between basins – typically performed manually – which is essential for effective filter aeration.

Given the scale of the infrastructure, Noria Conception Hydraulique proposed a fully automated system to the customer Terres de Montaigu. This decision shaped both the overall design and the choice of equipment, particularly the control valves.

A robust and easily integrated AVK solution

To address the automation needs, Noria Conception Hydraulique recommended AVK pneumatic knife gate valves, selected for their reliability, rapid actuation and robustness.

“Full automation is rare on this type of plant. We proposed this option with pneumatic valves during the tender phase. AVK valves seemed the right fit, both for their performance and ease of integration” explains Cyril COSSAIS, Project Manager at Noria Conception Hydraulique.

A total of 15 AVK knife gate valves (DN200) were supplied through our distribution partner LIBAUD AIZENAY. Installed in a buried concrete chamber weighing more than 25 tons, these pneumatic valves were chosen for their fast operation, reliability and proven long-term durability in wastewater handling, essential attributes for sanitation applications.

AVK Wastewater treatment plant - phyto-purification
AVK Wastewater treatment plant - phyto-purification

Straightforward installation and dependable performance

Cyril COSSAIS from Noria Conception Hydraulique emphasised the efficiency of the installation process:

“It’s a straightforward product – in the best possible way. Simple to install, reliable and requiring only minimal adjustments, mainly end-of-travel settings. A real time-saver.”

Since the commissioning in early March 2025, the station has been operating smoothly.

According to the customer, the installation fully meets expectations:

We wanted a reliable automation system to manage the treatment beds efficiently and avoid additional operating costs. Since the station was commissioned, the operator hasn’t reported any issues. Overall, I’m very satisfied with the installed equipment and how easy it is to use" says Sébastien BOURMAUD, Head of Sanitation for the Terres de Montaigu urban community.

A trusted partnership

Noria Conception Hydraulique has collaborated with AVK France for many years, enabling a seamless project execution. Thanks to their thorough knowledge of our product range, the company was able to propose a tailored technical solution during the bidding stage and support it through to commissioning. Once again, this installation highlights the strength of our partnership and the adaptability of our solutions to real‑world operational needs.

The knife gate valves were manufactured by CYL (an AVK subsidiary based in Spain), a specialised production site dedicated to custom gate valve solutions. This European manufacturing base ensures both responsiveness and consistently high performance.

Further projects are already in progress with Noria Conception Hydraulique, including the delivery of a DN400 motorised gate valve. A partnership that continues to grow.

Learn more about Knife gate valves here.

Case

Wastewater treatment plant with ground-breaking technologies

With the use of new technologies and energy-optimising equipment, the aim was to make the plant energy self-sufficient, and even produce 50% more energy than is consumed.
Read about the case

Expansion of the Los Vados wastewater treatment plant has increased the capacity of the system by three

Read about the case
Reducing energy consumption with AVK knife gate valves in Esbjerg, Denmark

Reducing energy consumption and service costs

Read about the case
Large butterfly valves ready for installation in a warehouse

Reliable valve solutions support environmental initiatives at high-end wastewater treatment plant

Read about the case
AVK valves installed at wastewater treatment plant in Mikkeli, Finland

State-of-the-art treatment technology in new wastewater plant

Read about the case
Features and installation of the knife gate valve - thumbnail

Animation

Knife gate valves

Animation about the features of our knife gate valves series 702.